Excavation projects : what to plan for
Before any excavation project, you need to request a utility locate through Info-Excavation (a free service in Quebec), check which permits your city or borough requires, plan access for the machinery, decide how the excavated soil will be removed, think about drainage, and account for the spring thaw, when load restrictions limit heavy trucks. Good preparation helps avoid delays, damage and unpleasant surprises.
Whether you're planning an addition, a French drain replacement, a new driveway or landscaping, excavation is often the first step, and it shapes everything that follows. Here's what to plan for.
Before you dig: locates and permits
Info-Excavation. Before any digging, a locate request must be submitted to Info-Excavation. This free service notifies the owners of underground networks, such as gas, electricity and telecommunications, who then mark the location of their lines, usually with paint or flags on the ground. Submit your request several days before the work begins.
Keep in mind that private installations, such as a power line running to a garage, an irrigation line or garden lighting, are generally not covered. Point them out to your contractor before the first shovel goes in.
Municipal permits. Depending on the work, a permit may be required: digging near a foundation, demolition, changing the curb cut for your driveway, cutting down a tree or occupying the street with equipment. Requirements vary from one city to the next, and in Montreal, from one borough to another. S&L checks with you what applies to your property before work begins.
Site access and protecting what stays
Excavation equipment needs room to get in, manoeuvre and load trucks. Before work starts, look at the width of the access route, fences that need to come down temporarily, overhead wires and whether the ground can support heavy machinery. Then think about what needs to stay intact:
- trees, whose roots often spread well beyond the trunk;
- your driveway and walkways, which heavy equipment can crack or shift without temporary protection;
- landscaping you want to keep, such as hedges, garden beds, a retaining wall or a patio;
- your neighbours, who should be notified before work starts, with property lines and a clean street respected throughout.
If the work comes close to the edge of your lot, your certificate of location helps pinpoint the property lines.
Excavated soil and bulk transport
People often underestimate how much soil a project produces. Once dug up, soil takes up more space than it did in the ground, because it's no longer compacted. Decide ahead of time what happens to it: some may be reused for backfill or grading, and the rest has to be hauled away.
On the flip side, many projects need materials brought in: stone for a base or a drain, gravel, sand or topsoil. S&L also handles bulk transport of these materials, which makes it easier to coordinate the excavation with the rest of the job. If structures need to be demolished, responsible debris management is part of the plan.
Plan for drainage from day one
Excavation changes the way water moves across your property, which makes it the right time to fix an existing problem: grading that sends water away from the house, where the downspouts discharge, a French drain, or the connection to a sump pit or the appropriate drainage system.
In the clay soils common across the West Island, water drains slowly. An open trench can fill up after a heavy rain, and the wrong backfill can hold water against the foundation. Choosing the right backfill material and compacting it in layers matters as much as the digging itself.
Timing and the spring thaw
In Quebec, load restrictions apply to heavy trucks during the spring thaw period. The dates are set each year by Quebec's transportation ministry according to zones, and they can be adjusted depending on the weather. During that period, hauling soil and materials may be restricted.
Thawing ground is also soft and waterlogged, which makes machinery work harder and can damage your yard. For many residential projects, late spring, summer and fall offer more favourable conditions. Planning over the winter lets you book the dates that suit you.
Getting the order right
Excavation almost always sets the stage for other work, and the order matters if you don't want to undo what was just done. The usual sequence looks like this:
- excavation and, where needed, demolition;
- underground work: French drain, foundation membrane, pipes;
- backfill compacted in layers, followed by grading;
- the granular base for new surfaces;
- finishing work: pavers, retaining walls, asphalt, sod and plantings.
Paving a driveway before replacing a French drain, for example, means tearing it up later. It's better to bring everything into one plan, even if the work is spread over more than one season.
Practical tipBefore work begins, walk the property with your contractor and take photos of the driveway, sidewalk, fences, trees and neighbouring yards. They'll serve as a reference point when it's time to restore the site.
In Lachine, Beaconsfield or Île-Bizard, a well-prepared project runs more smoothly, from the first shovelful to the finishing touches.
Frequently asked questions
Do I need to contact Info-Excavation before digging?
Yes. A locate request through Info-Excavation, free in Quebec, should be made in advance, before any digging. Private installations, such as a power line to a garage, are generally not covered.
Do I need a permit for excavation work?
It depends on the type of work and the municipality. In Montreal, requirements can also vary from one borough to another, so they should be checked before work begins.
Does the spring thaw affect an excavation project?
Yes. Load restrictions apply to heavy trucks during the thaw period, which can limit the hauling of soil and materials. Waterlogged ground also makes machinery work more difficult.